Project Initiation Meeting

Success Story of MGNREGS Works -------------------------------------------------- Name of the Scheme : MGNREGS Year 2011-12 Name of the Project : “Const of Cross Bandh at Alapaka Kahanalla ” Estimated Cost : Rs. 20000/- ( Rupees- Twenty Thousand ) only Work Code : 2402001001 / WC/ 1311555 Tech Sanction : 1813/ 2011 Dt. 28/11/2011 Fianacial Sanction : 1813 / 2011 Village- Alapaka GP- : Alapaka Block – Lephripara Executing Agency : Alapaka GP Name of the Gram Sanjojaks - Temba Tirkey, Alapaka The Project “Cross Bandh at Alapaka Kahanala” with an estimated cost of Rs.20000/- (Rupees- Twenty Thousand) only is initiated on the basis of labour demand in Form No. C1 by job seekers of Alapaka Village. Besides there is an urgent need to execute the work owing to its socio-economic benefits to the public. The Project Initiation Meeting for the project is held on 20/02/2012 to sensitize the labourers regarding the scheme, the work along with its measurement and payment procedure for work done. Sri Temba Tirkey of Alapaka Village of the GP who is the Gram Sanjojak for the project has tremendously educated and monitored the labours. The work is executed with the manual labour of 12 labourers w.e.f 23/02/2012 to 29/02/2012and 01/03/2012 to 07/03/2012 (with a weekly unpaid holiday). Photo of the project at pre-execution, during execution and completion stage has been taken. The Kahanala is a quasi-perennial water stream catering to the bathing needs and irrigation requirement of the locality. The water-source gets dries in May / June unless checked. The hamlet of Alapaka Basti and Colony Para take their bath in the checked stream. The boarders of Tunahara Ashram School existing adjacent to Alapaka GP Office also utilize the stream for bathing purpose only in acute summer working days. A group of farmers of the village undertake agricultural activities utilizing the water source and produce cereals, vegetables, pulses, etc. As a result the farmers are getting benefits economically. The expenditure incurred in the project generates more economic value and social benefits for the community than its costs. Thus its a successful initiative.

Under Progress


Completion

District : Sundargarh
Block : Lephripara
Panchayat : Lephripara
Financial Year : 2011-2012
Estimated Cost : 0.2
Start date : 23/02/2012
Expenditure Incurred : 0.19
Completion Date : 07/03/2012
« Back         « Previous        Next »