Imp. of Jhitiki Upper Kata Tank

It was unused take of village Jhitiki under Bisora GP. On demand of the Villagers the renovation work was taken up. The process of renovation has excavated silt 2379 number of mandays were generated by giving job opportunity to the job seekers of the village. Now water may retain throughout the year for use by villagers and cattle. The amount of Rs. 298875 /- has been spent towards renovation work. Irrigation facility can also be provided to about 10 acres of cultivated land in the monsoon season.

Pre Project


Under Progress

District : Nuapada
Block : Nuapada
Panchayat : Bisora
Financial Year : 2011-2012
Estimated Cost : 3.00
Start date : 09/06/2011
Expenditure Incurred : 2.98875
Labour Component : 370
Material Component : 1500
Mandays Generated : 2379
Completion Date : 15/06/2011